LienBuild home · Texas mechanics lien rules

Texas Mechanics Lien: Deadlines, Forms & Filing Rules

Texas mechanics lien rules cited to statute: monthly notice by the 15th of the 3rd month, lien affidavit by the 15th of the 4th/3rd month, suit within 1 year.

Monthly notice
15th of month 3

One notice per unpaid month: on commercial jobs, by the 15th day of the 3rd month after each unpaid month; on residential jobs, by the 15th of the 2nd month. Serve the owner and the original contractor (both are required).

Tex. Prop. Code §53.056(a-1)(1)

Residential: §53.056(a-1)(2) (2nd month). Each month stands alone — a missed notice forfeits that month’s lien rights.

Claim of lien
15th of month 4

Original contractor: record the sworn affidavit by the 15th day of the 4th month after the month work was completed, terminated, or abandoned (3rd month on residential). Lower-tier claimants anchor the same offsets to their last month of furnishing.

Tex. Prop. Code §53.052(a)(1)

Residential: §53.052(a)(2)/(c) (3rd month). Recorded with the county clerk (§53.052(a)).

Enforcement suit
1 year

Suit must be filed within 1 year after the last day the affidavit could be recorded (contracts signed on or after 01/01/2022). A recorded written agreement can extend the deadline to 2 years.

Tex. Prop. Code §53.158

Statute references verified 10/09/2026. Rules change — confirm the current text with the official state source before relying on a date.

How Texas's mechanics lien deadlines work

Texas mechanics lien law is Chapter 53 of the Property Code, and it runs on a monthly cycle that works differently from any other large state. A subcontractor or supplier on a commercial job who is not paid for a given billing period must send notice by the 15th day of the third month after that period, served on both the owner and the original contractor (Tex. Prop. Code §53.056(a-1)(1)). On residential jobs the notice is due by the 15th of the second month (§53.056(a-1)(2)). Each period stands alone: a missed notice forfeits that period's lien rights.

The lien itself is a sworn affidavit recorded with the county clerk of the county where the property sits (§53.054). For the original contractor, the recording deadline is anchored to the month in which the work was completed, terminated, or abandoned: the 15th day of the fourth month on commercial jobs (§53.052(a)(1)) and the 15th of the third month on residential jobs (§53.052(a)(2)). Lower-tier claimants anchor the same month offsets to their last month of furnishing (§53.052(b)-(c)). Within 5 days after recording, a copy of the affidavit must reach the owner — and the original contractor as well, for anyone who is not the original contractor (§53.055).

For contracts signed on or after 01/01/2022, a suit to enforce the lien must be filed within one year after the last day the affidavit could have been recorded (§53.158); a recorded written agreement can extend that to two years. Contracts signed before 01/01/2022 follow the pre-2022 rules. Homestead property adds its own formalities: the contract must be written, executed before the work or materials are furnished, signed by the owner and, if the owner is married, the owner’s spouse, and filed with the county clerk, or no lien attaches to the homestead (§53.254). The lien affidavit itself must carry the 10-point boldface notice "NOTICE: THIS IS NOT A LIEN. THIS IS ONLY AN AFFIDAVIT CLAIMING A LIEN." (§53.254(f)).

Who must send what

The notice duty depends on the role.

Original contractor (direct contract with the owner)

No monthly notice — the Chapter 53 notice duty applies to derivative claimants only (§53.056). On homestead jobs the contract must be written, executed before the work or materials are furnished, signed by the owner and, if the owner is married, the owner’s spouse, and filed with the county clerk, or there is no lien on the homestead (§53.254). Any lien affidavit on a homestead must also carry the statutory 10-point boldface notice (§53.254(f)). Residential contracts also carry a disclosure statement due before the contract is signed (§53.255) and a list of subcontractors and suppliers due before work begins (§53.256).

Subcontractor / supplier — commercial

One notice per unpaid period, due by the 15th day of the 3rd month after that period, served on the owner and the original contractor (§53.056(a-1)(1)). Skip a notice and that period carries no lien.

Subcontractor / supplier — residential

Notice due by the 15th day of the 2nd month after each unpaid period, served on both the owner and the original contractor (§53.056(a-1)(2)).

Specially fabricated materials

Notice due by the 15th day of the 2nd month after the order is accepted — measured from the order, not from later deliveries (§53.058).

Laborer

Treated as a derivative claimant for notice purposes: monthly notices follow the §53.056 schedule.

FAQ

Texas mechanics lien questions, answered straight.

When is a Texas mechanics lien due?

For an original contractor, the sworn affidavit must be recorded by the 15th day of the 4th month after the month the work was completed, terminated, or abandoned on a commercial job — the 15th of the 3rd month on a residential job (Tex. Prop. Code §53.052(a)). Subcontractors and suppliers anchor the same month offsets to their last month of furnishing (§53.052(b)-(c)). Recording is with the county clerk where the property sits (§53.054).

Who has to send monthly notices in Texas?

Subcontractors, suppliers, and laborers — everyone except the original contractor (§53.056). On commercial jobs, the notice for each unpaid period is due by the 15th of the 3rd month after that period (§53.056(a-1)(1)); on residential jobs, by the 15th of the 2nd month (§53.056(a-1)(2)). Both versions are served on the owner and the original contractor. Each period is independent — a missed notice forfeits that period’s lien rights.

Does a Texas mechanics lien need to be notarized?

Yes. The lien affidavit is a sworn statement recorded with the county clerk (§53.054). Recording costs vary by county: Harris County’s schedule listed $25 for the first page plus $4 for each additional page (per Harris County’s posted fee schedule, checked on 10/09/2026 — fees change).

What are the post-recording requirements in Texas?

Within 5 days after recording, the claimant must send a copy of the affidavit to the owner; anyone other than the original contractor must also send one to the original contractor (§53.055). The lien must then be enforced by suit within 1 year after the last day to record the affidavit, for contracts signed on or after 01/01/2022 (§53.158).

What is different about homestead property in Texas?

A lien on a homestead requires a written contract, executed before the work or materials are furnished, signed by the owner and, if the owner is married, the owner’s spouse, and filed with the county clerk (§53.254). The lien affidavit itself must carry the 10-point boldface notice "NOTICE: THIS IS NOT A LIEN. THIS IS ONLY AN AFFIDAVIT CLAIMING A LIEN." (§53.254(f)). Missing any of these formalities means no lien attaches to the homestead at all.

Ready to put the paperwork together?

Free state-specific forms, the deadline rules for every state we cover, and free generators for waivers, demand letters, and pay applications — built for contractors, not law firms.